Intermediate test before plasterboard: the self-builder's guide

Laid the membrane yourself? When to schedule the test before lining, what must be in place, and what you can still correct
27 November 2026 by
Intermediate test before plasterboard: the self-builder's guide

Laying your airtight membrane yourself? Before the plasterboard goes up, a leak takes ten minutes to fix; afterwards, it can take hours to find.

For a self-builder, the intermediate test is the best moment to check your work: the membrane is still visible, every leak can be seen and fixed on the spot. Here is how to prepare it and what it lets you correct.

The right moment: before plasterboard, before the linings

Schedule the intermediate test when:

  • the house is weathertight and closed in;
  • the external windows and doors are fitted and sealed;
  • the membrane or vapour barrier is laid, taped and counter-battened;
  • electrical conduits and services passing through the membrane are in place, and their airtightness is treated;
  • the plasterboard is not yet fitted.

What you can still correct at this stage

  • Overlaps and tapes on the membrane: a strip with too little overlap, tape that does not hold on a dusty surface.
  • Membrane connections to the floors and to the walls.
  • Penetrations: electrical conduits, high and low drains, ventilation ducts.
  • Window corners and membrane connections to the frames.
  • Loft hatch: perimeter seal and closure.

Have suitable sealant and your tapes ready on test day: many repairs are made during the leak search, with the house under depressurisation.

Test day

A blower door is fitted in an external opening and puts the house under depressurisation. We measure, then we look for leaks with you, room by room. You see directly where the air gets in, and you learn to spot weak points for the rest of your build.

What next?

Once the repairs are done, you fit your linings knowing the envelope holds. The final test, at handover, then validates the regulatory measurement and lets you obtain the Turnkey RE2020 certificate.

Further reading: The 2 right moments to test your house, the 5 most common leaks, and our page Airtightness testing for new RE2020 houses.