RE2020 airtightness test


Air permeability testing quantifies the airtightness defects of a building (unwanted air infiltration) by depressurising or pressurising houses, apartment buildings or commercial buildings.

Get the free guide (in French) Request a quote

High-performance building tested for RE2020 airtightness
Cover of the free EXP’AIR 67 guide

FREE GUIDE · 3 PAGES · IN FRENCH

The 2 right moments to test air permeability

4 out of 10 measurements fail at handover. Our guide shows you how to avoid being one of them.

  • When to schedule the intermediate test, and why it makes all the difference
  • The conditions for the final test and the value to achieve
  • The 5 most common leaks and the checklist to give your tradespeople

Get the free guide (in French)

Building envelope airtightness icon

Technique

What is building envelope airtightness testing?


Airtightness testing, or building air permeability measurement, shows the quality of a construction. The blower door test,

combined with leak detection, can be carried out on any type of building and ensures the durability of the structure and the comfort of its occupants.


Discover

Set-up and preparation

Our operators fit the blower door into the frame of the building’s main or secondary entrance door. The building is then prepared: air inlets and extract vents are temporarily sealed so that only unwanted leaks are measured.

Measurement and leak detection

The operators measure the envelope airtightness by pressurising or depressurising the building according to European standard ISO 9972 and French standard FD P50-784. Leak detection is then carried out at a pressure difference of 50 Pa to locate and fix envelope defects.

Writing the report

A test report compliant with current standards is drawn up, with the measurement results (Q4Pa-surf at 4 Pa and n50 at 50 Pa) and the main indicators required by RE2020 or the thermal calculation. Our reports always include detailed photos of envelope defects and located leaks.

Why carry out an airtightness test?


Energy savings

Air leaks in a building waste as much energy as poor insulation. In a new house, all the leaks together can add up to a hole several centimetres wide that is permanently open. Fixing the located leaks reduces heat loss.

Building durability

Air leaks cause excess moisture in the building structure (dew point). Reducing leaks and their flow rate therefore extends the life of the building.

Improving your insulation

And therefore your comfort. Insulation only works if the air it contains is still. Stopping air flow through insulation with suitable airtight membranes improves its performance and your thermal comfort.

What value must be achieved under RE2020?

The indicator measured is Q4Pa-surf: the leakage rate at 4 Pa divided by the surface area of the walls, in m³/(h.m²). The target is the value in your thermal study, within the limit of:

Building typeRE2020 limit (Q4Pa-surf)
Single-family house0.6 m³/(h.m²)
Apartment building1.0 m³/(h.m²)
Commercial buildings1.7 m³/(h.m²)

For commercial buildings, the measurement is mandatory for offices with a reference area of up to 3,000 m²; above that, it remains possible and is often requested by clients. See our tests for commercial buildings.

We also report n50 (air changes at 50 Pa), required by labels such as Passivhaus.

When should the test be done?

Intermediate test (recommended)

When the building is weathertight, with windows and membrane fitted, before the plasterboard goes up. Any leaks found can be fixed without dismantling anything.

Final test (mandatory)

Construction completed, ventilation installed. This is the report used for the RE2020 end-of-works certificate.

Guide gratuit EXP’AIR 67

Free guide (in French): the 2 right moments to test air permeability

When to schedule the intermediate test, the conditions for the final test and the checklist of the most common leaks.

Get the guide

Prices and lead times

ServicePrice
Intermediate test, single-family houseOn quotation
Final test, single-family houseOn quotation
Apartment buildingContact us
Commercial buildings, large volumes (multi-fan), all over FranceContact us

Intervention possible within 48 h in Alsace and the Grand Est. Report delivered within 24 to 48 h.

Request a quote

Frequently asked questions

What happens if the test fails?

We locate the leaks during the test, with photos. Once the contractors have fixed them, a new test confirms the result.

Do I need to be there during the test?

Yes, or someone who can open the building. We agree on the time slot together.

How should the building be prepared?

Windows and doors fitted and closed, electricity available, ventilation installed for the final test. We send you a checklist before our visit.

Who can carry out the final RE2020 test?

A Qualibat 8711 qualified operator, independent of the company that built the house. Exp’Air 67 has been Qualibat 8711 qualified since 2010.

Turnkey RE2020 certificate.

Our expertise

Qualibat logo: Exp’Air 67 is Qualibat 8711 and 8721 qualified

Our operators have been Qualibat 8711 qualified since 2010 and work together on site to keep testing lead times as short as possible. This is how we can guarantee reports within 24 or 48 hours, depending on how urgent our clients’ needs are.

Learn more

Blower door installed for an airtightness test

Our other services

Ventilation duct airtightness icon
Ventilation duct airtightness
+ 
Ultrasonic leak detection icon
Ultrasonic leak detection

+

Indoor air quality icon
Indoor air quality

+

Infrared thermography icon
Infrared thermography

+